
Pre-existing Duty Rule
The pre-existing duty
rule is a corollary to the requirement of consideration. Because consideration
that makes contracts enforceable must be “bargained for,” consideration cannot
consist of performance that the party had a pre-existing duty to perform. If
the party was legally required to do something in any case, then agreeing to do
that very thing is not new consideration that needs to have been “bargained
for” by the other party.[1] Therefore, a party’s offer
of a performance already required under an existing contract, employment term
or law is insufficient consideration for a new contract or the modification of
an existing contract.
As a practical matter,
the pre-existing duty rule also maintains the integrity of a contract by
preventing parties from using leverage to coerce the other parties into
contract modifications.[2] Let’s look at an example:
Two parties, a
contractor and a homeowner, enter into a contract for the renovation of a house.
A week later, the contractor becomes dissatisfied with how much he will be
paid. He tells the homeowner that he will walk away from the project unless he is
paid more for his services. Faced with the prospect of not having his desired
work completed, the homeowner agrees. Under the pre-existing rule, the homeowner’s
promise to pay the new amount is not enforceable because the contractor already
had a pre-existing duty to perform the work requested at the original price. There
has been no bargained-for-exchange for this modification and so the homeowner
will not have to pay more.
Some critics argue that
the rule can be too far-reaching because it makes contracts inflexible and
impedes modification that make sense. For example, say a plumber agrees to
replace all the piping inside a home with copper pipes, but before the project
starts, the price of copper skyrockets and it is no longer financially feasible
for the plumber to replace the pipe. The plumber might reasonably ask the
homeowner for additional payment to cover the cost of the increase in the price
of copper. However, even if the homeowner agrees to this modification, the
modification may not be binding under the pre-existing duty rule since the
plumber had a pre-existing duty to replace the piping with copper before the
modification.
While the pre-existing duty rule applies today,
these and other concerns have given rise to several exceptions to the rule.
The first exception occurs when one party acts
after relying on another party’s modification of a contract.[3] Moving back to our plumber
example, imagine that, after the homeowner agreed to pay a higher price, the
plumber, in reliance of that assurance, hired a high-quality subcontractor to
work on the piping. This good faith reliance on the modification may cause the
modification to be enforceable.
The second exception to
the rule is when unanticipated circumstances arise, leading to the parties to
agree upon a reasonable contract modification.[4] Examples of unanticipated
circumstances leading to required contract modification include:
·
Strikes;
·
Shortages;
·
Economic
depressions;
·
War;
and
·
Changed
construction conditions
When parties, in
response to these unanticipated emergencies, agree to modifications (generally
increased payments) in good faith, the modifications are enforceable in spite
of the fact that the called-for performance was pre-existing under the original
agreement.
The Uniform Commercial
Code, which applies to contracts for the sale of goods, also substantially
modifies the pre-existing duty rule. The UCC modifies the rule because it wants
to “assure contracting parties the ability to freely adapt to changing
circumstances.” UCC’s Section 2-209(1) provides:
“(1) An
agreement modifying a contract within this Article needs no consideration to be
binding.”[5]
Though
modification of sales contracts does not require new consideration, all
modifications must be made in good faith, which means “honesty in fact in the
conduct or transaction concerned.”[6] Good faith, for example,
does not occur when one party intentionally misled or deceived the other party
when seeking a sale of goods contract modification.
As early as 1938, one
judge called the pre-existing duty rule “one of the relics of antique law which
should have been discarded long ago.”[7] Despite its shortcomings,
the pre-existing duty rule does maintain contract integrity and can effectively
regulate contract modifications and prevent abusive practice in renegotiations.
To ensure that it remains useful, courts will continue to create exceptions to
it and place qualifications on its application.[8]
[1] Restat 2d of Contracts, § 89 (2nd 1981).
[2] Corneill Stephens, “Abandoning the
Pre-Existing Duty Rule: Eliminating the Unnecessary”, 8 Hous. Bus. & Tax
L.J. 355, (2008).
[3] Kevin Teevan, “A Legal History of
Binding Gratuitous Promises at Common Law: Justifiable Reliance and Moral
Obligation”, 43 Duq. L. Rev. 11, (2004).
[4]1A
Arthur Corbin, Corbin on Contracts § 172 (1950).
[5] U.C.C. § 2-209 (2003).
[6] U.C.C. § 2-104. (2003).
[7] Rye
v. Phillips, 282 N.W. 459, 460 (Minn. 1938).
[8] Michael Garrison and John Wendt, “Employee
Non-competes and Consideration: A Proposed Good Faith Standard for the
"Afterthought" Agreement”, 64 Kan. L. Rev. 409, (2015).