Promissory
Estoppel
The legal doctrine of promissory
estoppel is applied in all American states and finds its roots in equity.[1] In contract law,
promissory estoppel is an exception to the requirement of consideration for a
contract to be enforceable. Even in the absence of bargained-for exchange, a
promise is enforceable if the following three elements are satisfied:
1)
The promisor should reasonably expect to
induce action or forbearance from the promisee;
2)
Such action or forbearance is in fact
induced; and
3)
Injustice can be avoided only by
enforcement of the promise.[2]
We’ll address each of these elements,
the purposes of promissory estoppel, and how it’s used to prevent injustice.
Purpose of Promissory
Estoppel
Promissory estoppel was formally “ushered”
onto the stage of American contract law in 1932 in the First Restatement of
Contracts.[3] At the time, the
development of such a legal principle was viewed as a major departure from
classical contract law. Now, it is reserved for the limited class of cases
where it would be unconscionable or unfair to deny the promise upon which the
plaintiff has relied.[4]
Element 1: The
promissor should have reasonably expected to induce action or forbearance from
the promisee.[5]
Courts look at all the circumstances to
determine whether the promisor should have foreseen that the promisee would
rely on the promise. This may include looking at the communications between the
two parties to establish their states of mind. For example, if the promisee
told the promissor that he wanted to purchase a car but was $2,000 short of
being able to make a down payment, and the promissor then promised him $2,000,
the promissor should reasonably expect the promisee to make the down payment in
reliance of the promise. This reliance is reasonably foreseeable.
In Double AA Builders v. Grand State
Construction, an Arizona case, a general contractor solicited bids from
subcontractors for various portions of work on a larger project.[6] The general contractor
made the various bidders aware that their bids were for work on a larger
overall project. A subcontractor faxed a written but unsigned bid in the amount
of $115,000 for the work requested. The bid also stated, “Our price is good for 30 days.” The general contractor relied upon
the subcontractor’s bid to prepare its overall price for the construction
project and stopped taking other bids. Within 30 days, the subcontractor backed
out of the bid though. The general contractor had to find a replacement
subcontractor and paid the replacement company over $130,000 to complete the
same work. The contractor sued the subcontractor to enforce the original
promise.
The court ruled in favor of the general
contractor and reasoned that the subcontractor should have reasonably expected
the general contractor to use the subcontractor’s $115,000 bid to prepare his
overall price for the entire construction project. By including detailed
information in his bid, including the job name, scope of the work that would be
provided, the price for services, and payment terms, it was foreseeable that
the general contractor would rely on that bid to use in its own bid for the
overall project if the quote was lowest. This specified information was more than
just an expression of intent or desire to perform the work.
Element 2: Did the
promise induce such action or forbearance?
Second, a plaintiff will have to show
that there was a direct cause-effect relationship between the promisor’s
promise and the promisee’s action.
Quake Construction v. American Airlines, also involved a subcontractor dispute
about work on a construction project, but this time it was the subcontractor
who sued.[7] The plaintiff, the
subcontractor, alleged that it relied on an oral promise from an airline that
it was awarded a project to complete the expansion of the airline’s facilities
at O’Hare Airport in Chicago.
Promissory estoppel was applied and the
airline’s promise was enforceable even though it was unsupported by
consideration. The subcontractor had expanded its office space, hired a project
manager, and secured other subcontractors for the facility expansion project
all because of the oral promise. A direct cause and effect relationship existed
because the subcontractor would have no reason for taking all these actions in the absence of such a promise.
Element 3: Can
injustice be avoided by enforcement of the promise?
Courts interpret the term “injustice” to
mean an unfair result. If an unfair result would otherwise occur, a promise
will be enforced by awarding damages to a harmed party. Damages, however, are
limited to reliance damages, which means the amount of harm suffered
because of the reliance on the promise. While
courts generally prefer to award expectation damages, which means the full
promised value of the agreement, these are not necessarily available in
promissory estoppel cases. The court will award only those damages necessary to
avoid injustice.
For example, assume that a homeowner tells
an interior designer that he will hire the designer to remodel the home’s living
room and two bathrooms, but no binding contract is agreed to. The interior
designer spends money to purchase new wallpaper, new paint and tools necessary
for the remodeling. The day before the project begins, the homeowner backs out
and says he no longer needs the interior designer’s services. This is a classic example of where promissory estoppel may be applied. Although there was no binding
agreement between the parties, the designer detrimentally relied on the
homeowner’s promise.
What will a court award if the interior
designer is successful in a lawsuit against the homeowner? Most likely, it will
only award reliance damages, or the costs spent “in reliance” of the contract
performance, which is what is necessary to avoid injustice. As such, the
interior designer can recover the costs spent on wallpaper, paint, and tools,
but not the full amount that he would have earned had the project been
completed.
Promissory estoppel plays an important
role in American contract law to hold parties accountable and ensure equity, even
in the absence of consideration. It is a critical tool that courts can use to
avoid injustice when the general contract law rules would cause unfair results.
[1] Eric Mills Holmes, “The Four Phases of
Promissory Estoppel”, 20 Seattle U. L. Rev. 45, (1996).
[2] Eric Alden, “Rethinking Promissory
Estoppel”, 16 Nev. L.J. 659, (2016).
[3] Section 90, Restatement of the Law of
Contracts (Am. Law Inst. 1932).
[4] Meadow Ridge Capital, LLC v. Levi, 29
Misc. 3d 1224(A), (2010).
[5] Benjamin Boyer, “Promissory Estoppel:
Requirements and Limitations of the Doctrine”, 98 U. Pa. L. Rev. 459, (1950).
[6] Double
AA Builders, Ltd. v. Grand State Constr. L.L.C., 210 Ariz. 503, (2005).
[7] Quake
Constr., Inc. v. American Airlines, Inc., 141 Ill. 2d 281, (1990).